Construction progress
03/04/24

Construction progress for March 2024

LUCKY LAND by DIM is under construction.


We share the latest news from the construction site for March:


Building No. 3, Section 1:

  • arrangement of equipment of public places;
  • installation of access control systems;
  • setting up the navigation system.

Building No. 3, Section 2:

  • arrangement of equipment of public places;
  • installation of access control systems;
  • setting up the navigation system.

Building No. 3, Section 3:

  • arrangement of equipment of public places;
  • installation of access control systems;
  • setting up the navigation system.

Improvements, building No. 3:

  • arrangement of outdoor lighting;
  • arranging a fence;
  • landscaping of the territory continues.

Building No. 4, Section 1:

  • installation of risers K1, K2 B1, B2 and air conditioner drainage risers;
  • arrangement of apartment wiring of water supply and heating systems from the 3rd to the 13th floor;
  • installation of screeds in apartments and MZK from the 3rd to the 8th floor;
  • arrangement of risers and apartment wiring of EO systems;
  • installation of elevator equipment;
  • waterproofing of the terraces on the 3rd and 9th floors continues;
  • decoration of facades.

Building No. 4, Section 2:

  • installation of risers K1, K2, B1, B2 and air conditioner drainage risers;
  • arrangement of apartment wiring of water supply and heating systems from the 3rd to the 10th floor;
  • installation of screeds in apartments and MZK from the 5th to the 8th floor;
  • arrangement of risers and apartment wiring of EO systems;
  • installation of elevator equipment;
  • waterproofing of the terraces on the 3rd and 9th floors continues;
  • decoration of facades.

Building No. 4, Section 3:

  • installation of risers K1, K2, B1, B2 and air conditioner drainage risers;
  • arrangement of facades;
  • work is being carried out on the arrangement of finishing technical superstructures and ventilation shafts on the roof;
  • installation of elevator equipment;
  • installation of waterproofing of the terraces on the 3rd floor.

Building No. 4, external networks:

  • arrangement of external networks B1, K1, K2.

Building No. 5, Section 1:

  • work continues on the installation of vertical and horizontal elements of the monolithic frame on the 11th floor;
  • arrangement of walls and partitions 3, 6, 7 floors;
  • installation of ventilation units on the 9th and 10th floors;
  • the installation of staircases and landings on the 10th and 11th floors continues.

Building No. 5, Section 2:

  • work continues on the installation of vertical and horizontal elements of the monolithic frame on the 10th floor;
  • arrangement of walls and partitions 3, 4, 6, 7 floors;
  • installation of ventilation units 8, 9 floors;
  • installation of staircases and landings on the 9th floor.

Building No. 5, Section 3:

  • arrangement of vertical and horizontal elements of monolithic frame 4, 5, 6, 7 floors;
  • construction of monolithic stairs - 1st floor continues;
  • installation of staircases and platforms 2, 3, 4 floors;
  • installation of vertical waterproofing;
  • installation of ventilation units 2, 3 floors.

Building No. 5, section 1.6 (parking adjacent to section 3):

  • arrangement of the floor slab;
  • work on installation of vertical waterproofing continues;
  • backfilling of the underground part.

Building No. 5, section 1.5 (parking adjacent to sections 1-2):

  • work continues on the installation of vertical elements of the monolithic frame.

Building No. 6, Section 2:

  • installation of PVC structures on floors 2, 3, 4;
  • preparation of elevator shafts for installation of elevators.